Streetscape Construction
Santa Fe Drive is OPEN During Construction
Major infrastructure and streetscape improvements are now underway along Santa Fe Drive. Multiple agencies, utilities, contractors, and community partners are working throughout the corridor as part of this significant investment in Santa Fe Drive.
The Santa Fe Business Improvement District is working closely with project partners to keep our businesses, property owners, residents, customers, and community informed throughout construction.
Please continue to support Santa Fe Drive businesses during construction.
Current Work by Project
Water Main Replacement
This week, Denver Water crews will prepare for the final connection of the water main replacement project along Santa Fe Drive. The project remains on track for completion in early December.
The work involves connecting the newly installed water main in Santa Fe Drive to the existing 24-inch pipe, known as a conduit, along West 11th Avenue. To complete the connection safely, crews will temporarily drain the conduit and provide affected customers with water service through aboveground bypass piping. Denver Water has notified affected customers and is coordinating directly with them throughout the process.
Upcoming work includes:
Monday, Nov. 16: Service line transfers along Santa Fe Drive between West 11th and West 12th Avenues.
Tuesday, Nov. 17: Temporary bypass preparation at West 11th Avenue and Inca Street.
Wednesday, Nov. 18: Lead service line replacement between Kalamath Street and Santa Fe Drive and temporary bypass pipe installation between Mariposa and Galapago streets.
Thursday, Nov. 19: Water quality testing of the temporary bypass system.
Friday, Nov. 20: Transfer of affected properties to the temporary bypass and conduit draining along West 11th Avenue, pending successful water quality testing.
Saturday, Nov. 21, through Tuesday, Nov. 24 (tentative): Final connection of the new water main in Santa Fe Drive to the existing conduit along West 11th Avenue.
Schedule notes:
If weather or water quality testing delays the work, the final connection will move to the following weekend, with limited activity during Thanksgiving week.
Additional lead service line replacements and temporary bypass preparation will take place along West 11th Avenue between Mariposa and Galapago streets as crews coordinate directly with affected customers.
Denver Water Information
Customer Care: 303-893-2444
24/7 Emergency: 303-628-6801
Email: WaterUDoing@denverwater.org
Visit denverwater.org/SantaFe to sign up for project updates, submit questions, and provide feedback.
The current project information supplied to the BID states that work between West 10th and West 11th was expected to take approximately three to four weeks per block, with the overall pipe-replacement project scheduled for early 2027.
Streetscape Construction Contractor
Streetscape work is underway on Santa Fe Drive between 12th and 13th Avenues, including roadway removal and underground stormwater improvements. One lane of traffic remains open on Santa Fe Drive through this area, and on-street parking has been temporarily removed on both sides. The 13th Avenue intersection east of Santa Fe Drive will remain reduced to one lane while crews begin underground stormwater pipe replacement just north of the intersection. A full closure of 13th Avenue east of Santa Fe Drive is anticipated after the holiday week as work progresses south through the intersection. These traffic and parking impacts are expected to continue through spring 2027.
Updates will be shared through newsletters, flyers, and direct handouts to businesses and residents in the affected areas. We will continue providing information as construction progresses and conditions change.
To receive updates directly from the project team, sign up for construction updates here. Keeping businesses and residents informed is a key priority of the construction team. Reach out to our project team via the Project Hotline: (720) 335-5944. You can also visit the Project Website to learn more: denvergov.org/santafe.
Latest Construction Notice – August 2026
Santa Fe Drive Streetscape Improvements
This Vibrant Denver Bond program is making pedestrian, mobility, and safety improvements on Santa Fe Drive from 6th to 13th Avenues, installing wider sidewalks, upgrading drainage, improving intersections, adding new street lighting, significantly more trees and planters, and public art, while maintaining two lanes of travel and parking once complete – all the result of an extensive design process previously completed with businesses and residents in this community.
Improvements include:
- Wider sidewalks
- Improved pedestrian accessibility
- Drainage improvements
- Intersection improvements
- New street lighting
- Additional trees and landscaping
- Planters
- Public art
- Streetscape improvements
- Infrastructure improvements throughout the corridor
Once complete, Santa Fe Drive will maintain two lanes of travel and parking while providing a significantly improved pedestrian environment.
The project hotline is:
720-335-5944
The project description currently provided to the BID identifies improvements from 6th to 13th avenues, including wider sidewalks, drainage, intersections, lighting, trees, planters, and public art.
CONSTRUCTION NOTICE
Xcel Energy begins gas line work between W 6th and W 8th Avenues
Xcel Energy Utility Work
Xcel Energy progresses on gas line relocation work along Santa Fe between 6th and 8th Avenues. One lane of traffic will remain open on Santa Fe Drive during this work; street parking has been removed on both sides of Santa Fe between 6th and 8th Avenues.
Business access will remain open and accessible during construction. Driveway access will be maintained from either Santa Fe Drive or adjacent side streets, depending on the location of active work.
Outage & Safety – Report an Electric Outage
Contact the Project Hotline (720) 335-5944 for Xcel Energy questions and updates.
1-800-896-1999 for electric outages and downed lines
1-800-895-2999 for natural gas emergencies or gas odors
Travel Advisory & Resources
Stay connected!
Sign up for the Vibrant Denver Bond newsletter to receive the latest program news, project updates, and upcoming opportunities to get involved.
General city updates
You can also browse other topic-specific alerts and broad city summaries through the main Denver Sign-Up Center.
Recent news
To read current travel advisories and past announcements without signing up, check the DOTI News and Outreach page.
Business Support & Construction Impact Funding
Some of these resources will apply to businesses throughout the corridor, while others will depend on individual business eligibility:
Gap Loan Revolving Fund: This program provides below-market financing to help small businesses close funding gaps and reach their growth goals. Designed to support job creation, strengthen neighborhoods, and uplift underserved entrepreneurs, this program focuses on businesses operating in areas facing economic challenges.
BUILD Denver Program, in partnership with Colorado Enterprise Fund, is an affordable small business loan program. Applications are accepted on an ongoing basis.
New Denver Enterprise Zone Boundaries. The Denver Enterprise Zone Program offers tax credits to businesses in specific areas for activities like job creation, employee training, and investing in property. View the updated boundaries on the interactive Colorado Office of Economic Development and International Trade’s (OEDIT) website here.
Denver BizHub: The Denver BizHub is a centralized resource for small business owners to connect with City programs, technical assistance, financing resources, and other business support. Businesses can use the Hub to identify resources that fit their needs and get connected to additional assistance.
Business Resource Navigation: DEDO can help Santa Fe businesses identify programs, financing, and other resources that may fit their needs. Businesses that need additional support can contact Lauren Myerscough (lauren.myerscough@denvergov.org) by email to discuss their needs and identify appropriate next steps or referrals.
About the Project
Investing in the Future of Santa Fe Drive
The Santa Fe Drive Streetscape Project represents a major investment in the future of the corridor.
Construction is improving aging infrastructure while creating a safer, more accessible and welcoming Santa Fe Drive for businesses, residents, pedestrians, customers, visitors, artists, and the broader Denver community.
The project extends along Santa Fe Drive from approximately 6th Avenue to 13th Avenue.
The improvements include pedestrian, mobility, safety, drainage, lighting, landscaping, infrastructure, public-art and streetscape improvements.
Need Help?
Jackie Bouvier
Executive Director
Santa Fe Business Improvement District
Phone/Text: 720-838-8299
Email: director@santafebid.org
For Emergencies
Denver Water 24/7 Emergency:
303-628-6801
Streetscape Project Hotline
720-335-5944
Don't Miss an Update
Construction conditions can change quickly.
Sign up to receive Santa Fe BID updates so you know what is happening, where crews are working, changes to access, upcoming impacts, and other important information affecting the corridor.
Resources
Project Information
Coming soon
Construction Documents
Coming soon
Business Resources
Coming soon
Emergency / Reporting
Coming soon